Challenge
Faced with a Y2K problem and the availability of customer
choice within New Mexico the utility needed to quickly replace its
aging system with a new CIS.
Solution
TMG was selected to assist the utility in choosing and
implementing a new CIS. The evaluation and selection effort consisted
of the development of a design blueprint, development of an RFP,
review and grading of vendor proposals, identification of a vendor
finalist, solution confirmation activities, solution scoping activities,
contract negotiations and final review and approvals.
Result
The utility moved forward with a successful installation
of the product. Additional project phases were required to implement
other modules including Marketing and the Electronic Work Queue.
Type: Investor
Owned
Client Services: Electric
Accounts Served: 220,000
Population Served: 700,000
Project System: CIS
TMG Services: Evaluation & Selection, Installation
QA
Project Dates: 01/1998 - 05/1998
Go-Live: 08/1999 |