City of Mesa, Arizona
Challenge
Faced with retail choice in the electric market and increasing
customer service needs, the City initiated a procurement to select
and implement a new CIS solution by January 1, 2002.
Solution
TMG developed a design blueprint, developed
an RFP, received and evaluated vendor proposals, conducted vendor
confirmation activities, developed an installation plan, negotiated
contracts, and presented the solution for approval. The City selected
the SCT Banner solution.
Result
The installation was segmented into two phases. The first
phase implemented the base solution for deregulation in 12 months.
The second phase, which took six months, implemented additional
interfaces and an upgrade to version 3.0 -- a significant product
upgrade. The project was completed in December 2000.
Type:
Public Municipality
Client Services: Electric, Gas, Water, Wastewater,
Solid Waste, Recycling, Drainage, Other
Accounts Served: 125,000
Population Served: 500,000
Project System: CIS
TMG Services: Evaluation & Selection
Project Dates: 04/2000 - 12/2000
Go-Live: 01/2002 |