Challenge
El Paso Electric (EPE) had spent 3 years trying to implement SCT
Banner.
Solutions
TMG was engaged to provide a review of the SCT Banner Implementation.
The Review Team conducted three rapid assessments: review of the
current SCT Banner Implementation Project, analysis of the work
needed to complete the SCT Banner Implementation, and review of
the Enlogix Banner solution as a potential alternative approach.
It was concluded that with significant changes to the project structure,
staffing and focus, the Banner product implementation could be completed
in 13 months at a cost of $6.8 million. TMG further concluded that
with similar changes to the Project structure, Enlogix Banner can
be implemented in 12 months at a cost of $6.3 million.
Results
The Review Team recommended that EPE establish a contingency allowance
of $1.7 million to complete the SCT Banner project or $1.4 million
to complete the Enlogix Banner project. EPE executives approved
the recommendation and TMG began working with EPE and Enlogix on
contract negotiations and an installation plan.
Due to lack of funding, the EPE decided to discontinue the project.
Type:
Investor Owned
Client Services: Electric
Accounts Served: 310,000
Population Served: 564,000
Project System: CIS
TMG Services: Implementation Assessment
Project Dates: 01/2002 - 05/2002 |