There are many reasons why a CIS initiative fails, the following areas
of risk have been identified and presented for consideration.
CIS is not a proven solution.
The industry has moved from the implementation of custom developed solutions,
to the use of design guides or codeware customized specifically for
the utility, to product solutions with an 80 percent to 90 percent product
fit. In today's market a primary requirement is for the CIS product
to be installed at a minimum of one utility similar in size and services
provided. Those utilities selecting products still in development or
immature products with a minimal installed base have increased their
risk exponentially of extended implementation timeframes, cost overruns,
functional deficiencies, and in worst case scenarios outright project
failures.
Poor contract, scope and responsibilities.
A major source of project confusion can be attributed to poor contract
language, unclear scope definition and undefined responsibilities. Many
times the installation effort is initiated without the identification
of the project components necessary for a successful implementation
effort. In other instances, components or constructs may have been discussed
but never adequately documented and agreed to. During the implementation
effort the phrase “I assumed you were doing that.” is a
strong indicator that insufficient time was spent in defining project
scope and specific responsibilities.
Unrealistic expectations, timeframes and poorly defined costs.
Closely associated with second item, contracting parties frequently
enter the installation phase with unrealistic expectations of the other
party. This is why it is so important to perform an adequate level of
due diligence during the evaluation and selection effort. In a number
of efforts reviewed by TMG, project timeframes and identified costs
did not adequately allow for successful installation of the defined
solution. Many times project costs and associated project risks are
minimized in order to obtain approval for the installation effort only
to require subsequent funding requests.
Lack of available vendor resources.
Today's level of CIS market activity is significantly down compared
to recent years. As a result, layoffs, early retirement, etc., have
left many vendor's struggling to adequately staff projects with knowledgeable
product resources. A number of vendors have attempted to solve this
problem by forming relationships with Solution Integrators (SI) to supplement
staff. However, the use of SI's comes at a higher price tag resulting
in the utility paying high hourly rates for inexperienced product personnel.
On the other side, a few vendors continue to rely on internal consulting
groups to provide necessary project services. These groups are spread
very thin especially among fast growing CIS vendors with sales quickly
outpacing available resources.
Poor handoff from vendor sales to vendor operations.
Unfortunately, most selection efforts and final contract negotiations
are conducted with vendor sales personnel. Many times the details of
the agreed upon solution are never reviewed by vendor personnel responsible
for the installation effort. As a result, solutions are negotiated which
the vendor is not capable of fulfilling and projects are planned and
initiated which do not reflect the negotiated solution and utility expectations.
Vendors are beginning to add operational personnel to their sales teams
and require extensive review and approval throughout the organization
for new sales contracts. However, the issue remains a significant problem.
Customize rather than configure system.
For a utility to successfully implement and fully realize the ongoing
benefits of a product solution it must minimize customization work.
Vendors continue to enhance product flexibility through configuration
capabilities. Unfortunately, many utilities require the product to conform
to utility specific business requirements and processes. The utility
should only consider initial customization around required rates and
tariffs. All other customization should be delayed until the system
has been used in production. Utilities are modifying business processes,
rules of service, meter configurations, and even rate structures as
necessary to utilize the software. Every customization or interface
included within project scope increases the work effort and associated
project risk.
Utility does not dedicate project resources.
The utility tends to place all blame on the vendor for project troubles.
In reality, both the vendor and the utility are the source of problems.
One of the biggest issues which the utility faces is the inability to
adequately staff project positions with qualified business and technical
staff. Historically, TMG has seen part-time assignment with staff members
still responsible for production work or the utility assigns it's most
inexperienced or ineffective people to the project. More and more utilities
are waking up to the issue and backfilling for key personnel allowing
them to be dedicated to the project.
System is placed into production before its ready.
The biggest downfall of any project is the implementation of a system
which is not ready for production. At a workshop attended by 30 utilities
who recently implemented a CIS solution all 30 indicated they had implemented
their system before it was ready and did so to meet Executive/Board/Council
expectations around a go-live date which had been promised at the time
the solution was approved. While not as common there is another extreme
where a utility delays implementation until the system is 100 percent
complete—obviously this never occurs and the system is never implemented.
Users and customers not prepared. The project team
and certainly the vendor is focused on the design, configuration, testing
and implementation of the new solution. Training and communication becomes
the responsibility of the utility and is usually under funded, under
estimated and under delivered. User acceptance testing never occurs,
user classroom training is limited without mock production, refresher,
or ongoing education activities, and customer communication is limited
to a single bill insert notifying them of the new system. It is the
curse of most projects that while they are technical achievements they
are business failures with extensive resistance, business process issues,
education issues, and customer confusion.
Lack of executive involvement. The biggest underlying
reason most projects fail is the lack of strong executive involvement
and support of the project during its entire life-cycle. Most efforts
are initially approved by the executive team with their involvement
not occurring again until additional funding is requested, timeframes
are extended, or project success is placed in jeopardy. Usually executive
communication and support for the project occurs at the highest levels
in the utility and never effectively filters down to the staff level.
This lack of communication usually fuels staff resistance or a perception
of “This system will never be placed into production so why worry
about it.” syndrome which undermines staff participation and buy-in
to the solution. Executive involvement is more than a once a month status
report it is daily interaction, visibility and commitment by key executives
to the success of the effort.